INSTALLATION AF GAS ENGINE POWER PLANT

Location

Time: 2021-22 – 5 months
Place: Sulmona, Italy

Competences

60-70 pipe and steel fitters, mechanical fitters, welders, electricians and insulators worked on the project.

Led by DMA’s skilled Site Manager and supervisor team

Scope

A 4-engine gas-powered power plant will serve as a complement to the Sulmona area’s alternative energy sources.

On a fixed price contract, DMA has been responsible for civil – that is, everything following the foundation work, electrical and mechanical installation.